CONSOL ENERGY CENTER SITE PREPARATION

Overview

The SEA was responsible to deliver a clean site to the Penguins for construction of Consol Energy Center.

Key Facts

Abatement Construction Firms: Precision Environmental
  Allegheny Asbestos Analysis
  Professional Service Industries (PSI)
   
Demolition Construction Firms: Empire Dismantlement Corporation
  Homrich Incorporated
  Noralco Corporation
 
Infrastructure Construction Firm: W.G. Tomko, Inc.
   
Engineering Consultants: Resource International
 

Civil & Environmental Consultants (CEC)

  Raudenbush Engineering, Inc.
  ENSR Corporation
   
Total Estimated Site Prep Costs:  

Acquisition & Relocation Costs

$30 million

Hard Costs & Soft Costs

$10.8 million

Features

The first phase of site preparation involved property acquisition. The SEA acquired properties that will make up the 12.3 acre Consol Energy Center site.

The SEA commissioned an historical assessment of the Fifth Avenue buildings and the Epiphany Church & Rectory to identify historical significance of the structures. A report was filed with the Bureau of Historic Preservation as well as with the Pennsylvania Historical and Museum Commission.

The SEA advertised specs and bids for abatement and demolition of acquired properties. In addition to demolition, the SEA was responsible for relocating utility lines and applying for street vacations. Demolition and site preparation was completed in July of 2008.

Schedule

Properties Acquisition: August 2006 - December 2007
Abatement: April 2007 - Spring 2008
Demolition: July 2007 - Summer 2008
Delivery of Site: July 2008

Last Updated 5/19/10

Back to Top