ARENA GARAGE

Overview

Pursuant to the MOU, the Penguins have exercised the option to have a parking structure situated next to the arena. The development of a parking garage is a critical element in the Master Plan for the development of the Arena site.

Key Facts

Architect: Graves Architects, Inc.
Construction Manager: TBD
Facility Manager: TBD
Anticipated Development Cost: $9.13 million
Total Square Footage: 114,000 sq. ft.
Number of Spaces: 500
Levels: 4 (capacity to add extra floor)
Points of Ingress/Egress: 3
Construction Start: December 2008

Features

The parking structure is a 500-car four-story parking garage (with capacity for one additional floor) and is designed by Graves Architects, Inc. The parking garage can be entered and exited from Centre Avenue on the north at the top level of the garage or from Colwell Street on the south at the lowest level of the garage. The garage will connect to the arena for the use of suite and club seat holders during events. The garage will be used for commuter parking during the work day.

This parking structure is to be built by the SEA, and the budget is $9.13 million. The construction is funded by a 30-year revenue bond, which is backed, in part, by an annual from the Penguins. Any construction cost overruns are the responsibility of the SEA.

A site plan of the garage in relation to the arena can be found in the Master Plan.

Schedule

Design Start Date: September 2007
Master Planning Process: June 2007 - January 2008
Schematic Design Phase: September 2007 - October 2007
Design Development Phase: December 2007 - February 2008
Construction Document Phase: March 2008 - May 2008
100% Construction Documents: May 2008
Bid & Award: October 2008 - November 2008
Groundbreaking: December 2008
Construction Start: December 2008
Construction Final Completion: December 2009
Occupancy: August 2010

 

 

Last Updated 3/4/08