| Schematic Design Phase: |
September 2007 - October 2007 |
| Design Development Phase: |
December 2007 - November 2008 |
| Construction Document Phase: |
March 2009 - April 2009 |
| 100% Construction Documents: |
April 2009 |
| Bid & Award: |
October 2008 - February 2009 |
| Construction Final Completion: |
July 2010 |